A short practice note

Homebuyer rights under RERA: the Real Estate (Regulation and Development) Act 2016 — project registration, the 70% escrow account, delay compensation (s.18), complaints to the Authority and appeals

Lakshman Srikanth D

This note sets out, from the official Gazette of the Real Estate (Regulation and Development) Act, 2016 and the official Gazette notifications that brought its provisions into force, the statutory scheme on registration of real estate projects, the seventy per cent. separate account, delay compensation under section 18, complaints to the Real Estate Regulatory Authority, and appeals. It also records the holdings in M/s. Newtech Promoters and Developers Pvt. Ltd. v. State of UP & Ors. Etc. (11 November 2021), taken from the official Supreme Court of India PDF. Interest rates and forms are as may be prescribed by the appropriate Government or specified by regulations; this note does not treat any State’s rules as a uniform national rate.

The Act and its commencement

The Real Estate (Regulation and Development) Act, 2016 (Act No. 16 of 2016) received the assent of the President on 25 March 2016 and was published in the Gazette of India, Extraordinary, Part II, Section 1, No. 17, dated New Delhi, Saturday, 26 March 2016. Its long title is to establish the Real Estate Regulatory Authority for regulation and promotion of the real estate sector and to ensure sale of plot, apartment or building, as the case may be, or sale of real estate project, in an efficient and transparent manner and to protect the interest of consumers in the real estate sector, and to establish an adjudicating mechanism for speedy dispute redressal and also to establish the Appellate Tribunal to hear appeals from the decisions, directions or orders of the Authority and the adjudicating officer, and for matters connected therewith or incidental thereto. Section 1(2) of the 2016 Gazette provides that the Act extends to the whole of India except the State of Jammu and Kashmir. Section 1(3) provides that it shall come into force on such date as the Central Government may, by notification in the Official Gazette, appoint, and that different dates may be appointed for different provisions. Official Gazette of the Act hosted by the Ministry of Housing and Urban Affairs at https://rera.mohua.gov.in/images/pdf_folder/Real_Estate_Act_2016(1).pdf (CG / REGISTERED NO. DL—(N)04/0007/2003—16; Gazette dated 26 March 2016). This note quotes the 2016 Gazette text of section 1(2) as published; a later official notification extending the Act to the Union territories of Jammu and Kashmir and Ladakh, if any, is not among the official PDFs obtained for this note.

By S.O. 1544(E) dated 26 April 2016, published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 990, dated New Delhi, Wednesday, 27 April 2016, the Central Government, in exercise of section 1(3), appointed 1 May 2016 as the date on which section 2, sections 20 to 39, sections 41 to 58, sections 71 to 78, and sections 81 to 92 came into force.

In exercise of the powers conferred by sub-section (3) of section 1 of the Real Estate (Regulation and Development) Act, 2016 (16 of 2016), the Central Government hereby appoints the 1st day of May, 2016 as the date on which the following provisions of the said Act shall come into force, namely:–

1. Section 2; 2. Sections 20 to 39; 3. Sections 41 to 58; 4. Sections 71 to 78; 5. Sections 81 to 92.

S.O. 1544(E), 26 April 2016, official Gazette notification hosted by the Ministry of Housing and Urban Affairs at https://rera.mohua.gov.in/images/pdf_folder/Commencement_of_RERA_in_2016.pdf.

By S.O. 1216(E) dated 19 April 2017, published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 1075, dated New Delhi, Wednesday, 19 April 2017, the Central Government appointed 1 May 2017 as the date on which sections 3 to 19, section 40, sections 59 to 70, and sections 79 to 80 came into force. Project registration, the seventy per cent. account, the promoter’s delayed-possession liability under section 18, and the allottee’s corresponding right under section 19(4) are therefore among the provisions in force from 1 May 2017. The Authority, the adjudicating officer (section 71) and the Appellate Tribunal (section 43) rest on provisions that had already been appointed to come into force on 1 May 2016, except that recovery under section 40 came into force on 1 May 2017.

In exercise of the powers conferred by sub-section (3) of section 1 of the Real Estate (Regulation and Development) Act, 2016 (16 of 2016), the Central Government hereby appoints the 1st day of May, 2017 as the date on which the following provisions of the said Act shall come into force, namely:—

1. Section 3 to 19; 2. Section 40; 3. Section 59 to 70; 4. Section 79 to 80.

S.O. 1216(E), 19 April 2017, official Gazette notification hosted by the Ministry of Housing and Urban Affairs at https://rera.mohua.gov.in/images/pdf_folder/commencement_of_remaining_sections_of_RERA_in_2017.pdf.

By S.O. 2287(E) dated 7 May 2026, the Central Government, in exercise of section 1(2) of the Jan Vishwas (Amendment of Provisions) Act, 2026 (Act 8 of 2026), appointed the date of publication of that notification as the date on which the provisions of that Act, insofar as they relate to serial number 70 and the entries relating thereto in the Schedule to that Act relating to the Real Estate (Regulation and Development) Act, 2016, came into force. The official Gazette is hosted by the Ministry under a heading referring to the amended provision of section 68. An official PDF of Act 8 of 2026 itself was not obtained for this note, so the substituted text of section 68 is not quoted here. S.O. 2287(E), 7 May 2026, Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 2196 (CG-DL-E-07052026-272317), official Gazette notification hosted by the Ministry of Housing and Urban Affairs at https://rera.mohua.gov.in/images/pdf_folder/Gazette%20Notification%20dated%2007.05.2026%20regarding%20the%20amended%20provision%20of%20RERA%20(Section%2068).pdf.

Project registration

Section 3(1), in force from 1 May 2017, provides that no promoter shall advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in any planning area, without registering the real estate project with the Real Estate Regulatory Authority established under the Act. Projects that are ongoing on the date of commencement of the Act and for which the completion certificate has not been issued must be made the subject of an application for registration within a period of three months from the date of commencement of the Act. If the Authority thinks necessary, in the interest of allottees, for projects developed beyond the planning area but with the requisite permission of the local authority, it may, by order, direct the promoter of such project to register. The Explanation to section 3 provides that where the real estate project is to be developed in phases, every such phase shall be considered a stand alone real estate project, and the promoter shall obtain registration under the Act for each phase separately.

Section 3(2) provides that no registration shall be required where the area of land proposed to be developed does not exceed five hundred square meters or the number of apartments proposed to be developed does not exceed eight inclusive of all phases (the appropriate Government may reduce that threshold); where the promoter has received completion certificate for a real estate project prior to commencement of the Act; or for renovation or repair or re-development which does not involve marketing, advertising selling or new allotment of any apartment, plot or building, as the case may be, under the real estate project. The phrase “marketing, advertising selling” is as it appears in the official Gazette.

Section 4(1) requires every promoter to make an application to the Authority for registration of the real estate project in such form, manner, within such time and accompanied by such fee as may be specified by the regulations made by the Authority. Section 4(2) requires the application to enclose the documents there listed, including a declaration, supported by an affidavit, as to title, encumbrances, the time period for completion, the seventy per cent. account described below, pending approvals, and such other documents as may be prescribed.

Section 5(1) provides that, on receipt of the application, the Authority shall within a period of thirty days grant registration, subject to the Act and the rules and regulations, and provide a registration number, including a Login Id and password, or reject the application for reasons to be recorded in writing, if it does not conform to the Act or the rules or regulations: provided that no application shall be rejected unless the applicant has been given an opportunity of being heard. The official Gazette begins that sub-section “On recipt of the application”. Section 5(2) provides that if the Authority fails to grant the registration or reject the application within that period, the project shall be deemed to have been registered, and the Authority shall within seven days of the expiry of the thirty days provide a registration number and a Login Id and password. The registration granted is valid for the period declared by the promoter under section 4(2)(l)(C) for completion of the project or phase (the official Gazette of section 5(3) refers to “sub-clause (C) of clause (1) of sub-section (2) of section 4”).

Section 6 provides that the registration may be extended by the Authority on an application made by the promoter due to force majeure, in such form and on payment of such fee as may be specified by regulations. The Authority may also, in reasonable circumstances, without default on the part of the promoter, based on the facts of each case, and for reasons to be recorded in writing, extend the registration for such time as it considers necessary, which shall, in aggregate, not exceed a period of one year. No application for extension shall be rejected unless the applicant has been given an opportunity of being heard. For this section, “force majeure” means a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project. Section 7 provides for revocation of registration on receipt of a complaint or suo motu or on the recommendation of the competent authority, on the grounds and in the manner there stated.

The seventy per cent. separate account

Section 4(2)(l)(D) requires the promoter’s affidavit to state that seventy per cent. of the amounts realised for the real estate project from the allottees, from time to time, shall be deposited in a separate account to be maintained in a scheduled bank to cover the cost of construction and the land cost and shall be used only for that purpose. The official provisos then qualify withdrawal from that account:

Provided that the promoter shall withdraw the amounts from the separate account, to cover the cost of the project, in proportion to the percentage of completion of the project:

Provided further that the amounts from the separate account shall be withdrawn by the promoter after it is certified by an engineer, an architect and a chartered accountant in practice that the withdrawal is in proportion to the percentage of completion of the project:

Provided also that the promoter shall get his accounts audited within six months after the end of every financial year by a chartered accountant in practice, and shall produce a statement of accounts duly certified and signed by such chartered accountant and it shall be verified during the audit that the amounts collected for a particular project have been utilised for the project and the withdrawal has been in compliance with the proportion to the percentage of completion of the project.

Explanation.— For the purpose of this clause, the term “schedule bank” means a bank included in the Second Schduled to the Reserve Bank of India Act, 1934.

Section 4(2)(l)(D) of the official Gazette of the Act hosted at https://rera.mohua.gov.in/images/pdf_folder/Real_Estate_Act_2016(1).pdf. The words “schedule bank” and “Second Schduled” are as they appear in that official Gazette.

Delay compensation under section 18

Section 18, headed in the official margin “Return of amount and compensation”, provides:

(1) If the promoter fails to complete or is unable to give possession of an apartment, plot or building,—

(a) in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b) due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,

he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act:

Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.

(2) The promoter shall compensate the allottees in case of any loss caused to him due to defective title of the land, on which the project is being developed or has been developed, in the manner as provided under this Act, and the claim for compensation under this sub-section shall not be barred by limitation provided under any law for the time being in force.

(3) If the promoter fails to discharge any other obligations imposed on him under this Act or the rules or regulations made thereunder or in accordance with the terms and conditions of the agreement for sale, he shall be liable to pay such compensation to the allottees, in the manner as provided under this Act.

Section 18 of the official Gazette of the Act hosted at https://rera.mohua.gov.in/images/pdf_folder/Real_Estate_Act_2016(1).pdf. The rate of interest is “as may be prescribed”; this note does not quote any State’s prescribed rate as if it were a uniform central figure.

Section 19(4) confers a corresponding right on the allottee: the allottee shall be entitled to claim the refund of amount paid along with interest at such rate as may be prescribed and compensation in the manner as provided under the Act, from the promoter, if the promoter fails to comply or is unable to give possession of the apartment, plot or building, as the case may be, in accordance with the terms of agreement for sale or due to discontinuance of his business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder. Section 19 also entitles the allottee to information relating to sanctioned plans and to the stage-wise time schedule of completion, and to claim possession as per the promoter’s declaration of the completion period under section 4(2)(l)(C). The allottee who has entered into an agreement for sale under section 13 is responsible to make necessary payments as specified in that agreement, and is liable to pay interest, at such rate as may be prescribed, for any delay in such payment, subject to reduction when mutually agreed.

Complaints to the Authority and the adjudicating officer

Section 31(1) provides that any aggrieved person may file a complaint with the Authority or the adjudicating officer, as the case may be, for any violation or contravention of the provisions of the Act or the rules and regulations made thereunder against any promoter, allottee or real estate agent, as the case may be. The official Gazette reads “against any promoter allottee or real estate agent, as the cae may be.” The Explanation states that, for this sub-section, “person” shall include the association of allottees or any voluntary consumer association registered under any law for the time being in force. The form, manner and fees for filing the complaint shall be such as may be specified by regulations.

Section 71(1) provides that, for the purpose of adjudging compensation under sections 12, 14, 18 and section 19, the Authority shall appoint, in consultation with the appropriate Government, one or more judicial officer as deemed necessary, who is or has been a District Judge, to be an adjudicating officer for holding an inquiry in the prescribed manner, after giving any person concerned a reasonable opportunity of being heard. A person whose complaint in respect of those matters is pending before a Consumer Disputes Redressal Forum or Commission under the Consumer Protection Act, 1986, on or before the commencement of the 2016 Act, may, with the permission of such Forum or Commission, withdraw that complaint and file an application before the adjudicating officer. The application is to be dealt with as expeditiously as possible and disposed of within sixty days from receipt, with reasons in writing if that period is exceeded. Section 72 sets out the factors to be taken into account while adjudging the quantum of compensation or interest.

Appeals

Section 43(1) requires the appropriate Government, within a period of one year from the date of coming into force of the Act, to establish an Appellate Tribunal to be known as the (name of the State/Union territory) Real Estate Appellate Tribunal. Until that Tribunal is established, the appropriate Government shall designate, by order, any Appellate Tribunal functioning under any law for the time being in force to hear appeals under the Act. Section 43(5) provides that any person aggrieved by any direction or decision or order made by the Authority or by an adjudicating officer under the Act may prefer an appeal before the Appellate Tribunal having jurisdiction over the matter:

Provided that where a promoter files an appeal with the Appellate Tribunal, it shall not be entertatined, without the prmoter first having deposited with the Appellate Tribunal atleast thirty per cent. of the penalty, or such higher percentage as may be determined by the Appellate Tribunal, or the total amount to be paid to the allottee including interest and compensation imposed on him, if any, or with both, as the case may be, before the said appeal is heard.

Proviso to section 43(5) of the official Gazette of the Act hosted at https://rera.mohua.gov.in/images/pdf_folder/Real_Estate_Act_2016(1).pdf. The spellings “entertatined”, “prmoter”, “atleast” and, earlier in the same sub-section, “jusrisdiction” are as they appear in that official Gazette.

Section 44 provides that the appropriate Government or the competent authority or any person aggrieved by any direction or order or decision of the Authority or the adjudicating officer may prefer an appeal to the Appellate Tribunal, within a period of sixty days from the date on which a copy of the direction, order or decision is received, in such form and accompanied by such fee as may be prescribed. The Tribunal may entertain an appeal after the expiry of sixty days if it is satisfied that there was sufficient cause for not filing it within that period (the official Gazette reads “not filling it”). The Tribunal may, after giving the parties an opportunity of being heard, pass such orders, including interim orders, as it thinks fit, and shall endeavour to dispose of the appeal within a period of sixty days from the date of receipt of the appeal. A further appeal from the Tribunal to the High Court lies under section 58, on one or more of the grounds specified in section 100 of the Code of Civil Procedure, 1908.

The judgment in Newtech Promoters (11 November 2021)

In M/s. Newtech Promoters and Developers Pvt. Ltd. v. State of UP & Ors. Etc., Civil Appeal Nos. 6745–6749 of 2021 (with connected appeals), decided on 11 November 2021, a three-Judge Bench (Uday Umesh Lalit, Ajay Rastogi and Aniruddha Bose JJ.) heard a batch of appeals by promoters against orders of the Allahabad High Court which had dismissed writ petitions challenging orders of a single member of the Uttar Pradesh Real Estate Regulatory Authority directing refund with interest, and challenging the condition of pre-deposit under the proviso to section 43(5). The judgment, delivered by Rastogi J., framed five questions and answered them as follows.

On whether the Act is retrospective or retroactive, the Court held that its application is retroactive in character. Projects already completed or to which the completion certificate has been granted are not under its fold, and vested or accrued rights, if any, are in no manner affected. At the same time, it will apply after getting the on-going projects and future projects registered under section 3 to prospectively follow the mandate of the Act. The Court recorded that the Parliament intended to bring ongoing projects, where the completion certificate has not been issued, within the fold of the Act under section 3(1).

On whether the Authority or the adjudicating officer has jurisdiction to direct return or refund under sections 12, 14, 18 and 19, the Court held that when it comes to refund of the amount, and interest on the refund amount, or directing payment of interest for delayed delivery of possession, or penalty and interest thereon, it is the regulatory authority which has the power to examine and determine the outcome of a complaint; and that when it comes to seeking the relief of adjudging compensation and interest thereon under sections 12, 14, 18 and 19, the adjudicating officer exclusively has the power to determine, keeping in view the collective reading of section 71 read with section 72.

From the scheme of the Act of which a detailed reference has been made and taking note of power of adjudication delineated with the regulatory authority and adjudicating officer, what finally culls out is that although the Act indicates the distinct expressions like ‘refund’, ‘interest’, ‘penalty’ and ‘compensation’, a conjoint reading of Sections 18 and 19 clearly manifests that when it comes to refund of the amount, and interest on the refund amount, or directing payment of interest for delayed delivery of possession, or penalty and interest thereon, it is the regulatory authority which has the power to examine and determine the outcome of a complaint. At the same time, when it comes to a question of seeking the relief of adjudging compensation and interest thereon under Sections 12, 14, 18 and 19, the adjudicating officer exclusively has the power to determine, keeping in view the collective reading of Section 71 read with Section 72 of the Act.

Official Supreme Court of India PDF of the judgment dated 11 November 2021 in Civil Appeal Nos. 6745–6749 of 2021, M/s. Newtech Promoters and Developers Pvt. Ltd. v. State of UP & Ors. Etc., at https://api.sci.gov.in/supremecourt/2021/5013/5013_2021_14_1502_31099_Judgement_11-Nov-2021.pdf, paragraph 86 (Question no. 2).

On whether section 81 authorises the Authority to delegate its powers to a single member to hear complaints under section 31, the Court held that the power of delegation under section 81 by the Authority to one of its members for deciding applications or complaints under section 31 is well defined and expressly permissible. It also held that the powers of the adjudicating officer appointed under section 71 are not delegable under section 81.

On the condition of pre-deposit under the proviso to section 43(5), the Court held that the obligation cast upon the promoter of pre-deposit, being a class in itself, can in no circumstance be said to be onerous as prayed for or in violation of Articles 14 or 19(1)(g) of the Constitution. On recovery, the Court held that the amount which has been determined and is refundable to the allottees or home buyers, either by the Authority or the adjudicating officer, is recoverable within the ambit of section 40(1). The batch of appeals was disposed of, with liberty to a promoter who intended to prefer an appeal before the Appellate Tribunal against the order of the Authority to do so within 30 days, provided the condition of pre-deposit under the proviso to section 43(5) was complied with.

For a structured reading of the official text of the Act, the commencement notifications and the judgment discussed above, with subsequent official updates, see SooperKanoon.

This note is not legal advice and is not a complete statement of the law on real estate regulation, including any later official amendment of the Act (other than the commencement, by S.O. 2287(E), of serial number 70 of the Schedule to the Jan Vishwas (Amendment of Provisions) Act, 2026, the substituted text of which is not quoted here), any rules or regulations of an appropriate Government or Authority, or the practice of any Real Estate Regulatory Authority or Appellate Tribunal. The quotations and dates above were checked against the official Gazette of the Act and the official Gazette notifications of S.O. 1544(E), S.O. 1216(E) and S.O. 2287(E) hosted by the Ministry of Housing and Urban Affairs at the https://rera.mohua.gov.in/images/pdf_folder/ paths cited in the notes above, and against the official Supreme Court of India PDF of the judgment dated 11 November 2021 in Civil Appeal Nos. 6745–6749 of 2021. Confirm the current official text, including the rules prescribed for the relevant State or Union territory, from the Official Gazette or from the Ministry or the concerned Authority, before relying on a particular provision.